top of page

PROCESS

Please click on each item for more detail.

​

The main stages below include general timescales for completion from start of each stage. These assume swift responses from clients, consultants, and local authorities. A best case scenario assuming immediate responses from those involved, a standard project would take 14-20 weeks to receive a decision on a planning application. However, we recommend clients allow a minimum of 6 months from commencement of works to receipt of a planning decision and another 3 to 6 months beyond that until commencement on construction on site.

Preliminary Stage

  • 01
  • 02
  • 03
  • 04
  • 05

Planning Stage

  • 01
  • 02
  • 03
  • 04

Construction Stage

  • 01
  • 02
  • 03
  • 04

FULL PROCESS

Click image to enlarge

Project Flowchart with logo.jpg
bottom of page