PROCESS

Please click on each item for more detail.

The main stages below include general timescales for completion from start of each stage. These assume swift responses from clients, consultants, and local authorities. A best case scenario assuming immediate responses from those involved, a standard project would take 14-20 weeks to receive a decision on a planning application. However, we recommend clients allow a minimum of 6 months from commencement of works to receipt of a planning decision and another 3 to 6 months beyond that until commencement on construction on site.

Preliminary Stage

Planning Stage

Construction Stage

FULL PROCESS

Click image to enlarge

Project Flowchart with logo.jpg